In the Town of Comox, building permits are issued under Comox Building Bylaw 1472, through Development Services. The bylaw's permit rule covers repairing as well as constructing and altering, but it doesn't define repair or mention re-roofing, and the Town's permit page doesn't either. We confirm per address with the Town before any Comox roof is booked.

Reviewed by Scott Plumptree, Director of Marketing, The Interlock Group · Updated October 24, 2026

Consultations on Zoom or at your home. Book a Zoom consultation

Permits issued by

Town of Comox, Development Services (Building Department), 250-339-1118

comox.ca

Building bylaw

Comox Building Bylaw 1472 (consolidated January 15, 2025)

comox.ca

Processing time

2–4 weeks for complete applications, depending on complexity

comox.ca

Tree bylaw

Tree Protection Bylaw No. 2063; a Tree Permit to cut or remove a Regulated Tree

comox.ca

Who issues building permits in Comox

The Town of Comox issues its own building permits. Its Get a Building Permit page says applications can be submitted through the PSD Citywide portal, that the Town aims to process complete applications within 2–4 weeks depending on complexity, and that each permit is reviewed by more than one department: Building, Engineering for servicing and driveways, and Planning for zoning. Development Services staff answer questions at 250-339-1118.

What Comox Building Bylaw 1472 says

Section 4(1) of the bylaw says "A permit is required whenever work regulated under this bylaw is to be undertaken." Section 8(2)(a) says an owner must get a building permit first, and the work it lists includes "repairing" as well as constructing and altering. Section 5(2) says the bylaw doesn't apply to buildings or structures exempted by Part 1 of the Building Code.

The bylaw doesn't define "repair" or say anything specific about replacing a roof covering, and the Town's permit page is silent on re-roofing too. With wording that broad, we don't guess. We ask the Town about your address and the scope of the job.

When a Comox roof job becomes structural

Cutting in a skylight, building a dormer, beefing up rafters or steepening the pitch is altering the structure, which the bylaw plainly brings under a permit. The bylaw also lets a building official ask for "a roof plan and roof height calculations," so a change to the roof's shape can mean drawings. Rotten decking or a cracked rafter sometimes only shows up during tear-off; when that happens on a Comox job, the crew pauses and we call you before anything structural is touched.

Development permit areas and trees in Comox

The Town's permit page says Planning checks each application against "applicable Development Permit Area requirements." If your lot is in a development permit area, the Town will tell us whether that matters for a roof job.

Trees are regulated under Tree Protection Bylaw No. 2063. The Town's tree permit page says "If you plan to Cut or Remove a Regulated Tree, a Tree Permit is required unless a certain circumstance applies," and that trees on Town-owned or Town-managed land are protected regardless of size. Pruning that follows best practices, without removing more than 25% of live foliage or topping, is exempt. If a tree over your roof needs work before the crew arrives, check with the Town first.

How we handle permits for a Comox roof

At the estimate we note what the job involves and anything structural. We confirm the requirement for each address with the Town of Comox, and if a permit is needed, we apply for it and book the inspections before the job is scheduled. Townhouse and condo owners in a strata need council approval before we book. Bylaw 1472 is amended from time to time; the version quoted here is the consolidation dated January 15, 2025, and we recheck before each job.

Comox questions, answered

Does the Town of Comox or the Comox Valley Regional District handle my permit?

If your house is inside the Town of Comox, the Town handles it under its own Building Bylaw 1472. Properties outside the Town boundary are covered by other offices, so we confirm which one applies from your address before we quote.

How long does a Comox building permit take?

The Town says it aims to process building permits within 2–4 weeks for complete applications, depending on how complex the project is. We build the Town's timeline into your schedule rather than book a start date we can't keep.

A big fir is hanging over my Comox roof. Can I cut it before the new roof goes on?

Check first. Under Tree Protection Bylaw No. 2063, cutting or removing a Regulated Tree needs a Tree Permit unless an exception in Section 5 applies. The Town's page explains how to measure the trunk at 1.4 metres up. Careful pruning within best practices is exempt.

Sources for this Comox guide

  1. Town of Comox — Get a Building Permit
  2. Town of Comox — Building Bylaw 1472, consolidated January 15, 2025 (PDF)
  3. Town of Comox — Tree Permit
  4. Town of Comox — Tree Protection Bylaw

Product specifications are the manufacturer's (Interlock Roofing). Install counts are from our own job book. Reviewed by Scott Plumptree, October 24, 2026.